4                                            Air Quality Impact Assessment

4.1                                      Introduction

This Section presents an assessment of the potential air quality impacts associated with the construction and operation of the Project.

4.2                                      Legislation Requirements and Evaluation Criteria

The principal legislation for the management of air quality in Hong Kong is the Air Pollution Control Ordinance (APCO) (Cap. 311).  Under the APCO, the Hong Kong Air Quality Objectives (AQOs), which are presented in Table 4.1, stipulate the statutory limits for air pollutants and the maximum allowable numbers of exceedences over specific periods.

Table 4.1        Hong Kong Air Quality Objectives (mg m-3) (a)

Air Pollutant

Averaging Time

 

1 Hour (b)

8 Hour (c)

24 Hour (c)

3 Months (d)

1 Year (d)

Total Suspended Particulates (TSP)

-

-

260

-

80

Respirable Suspended Particulates (RSP) (e)

-

-

180

-

55

Sulphur Dioxide (SO2)

800

-

350

-

80

Nitrogen Dioxide (NO2)

300

-

150

-

80

Carbon Monoxide (CO)

30,000

10,000

-

-

-

Photochemical Oxidants (as ozone (O3)) (f)

240

-

-

-

-

Lead (Pb)

-

-

-

1.5

-

Notes:

(a)       Measured at 298K (25°C) and 101.325 kPa (one atmosphere)

(b)       Not to be exceeded more than three times per year

(c)        Not to be exceeded more than once per year

(d)       Arithmetic means

(e)       Suspended airborne particulates with a nominal aerodynamic diameter of 10 micrometres or smaller

(f)         Photochemical oxidants are determined by measurement of ozone only

In addition, the Technical Memorandum of Environmental Impact Assessment Ordinance (EIAO-TM) stipulates an hourly TSP criterion of 500 mg m-3 for construction dust impact assessment.

The measures stipulated in the Air Pollution Control (Construction Dust) Regulations should be followed to reduce dust impacts.

4.3                                      Baseline Conditions

The Project area is located at the Hong Kong boundary.  Villages are located to the south or southeast of the river.  No commercial and industrial developments are identified within the Study Area (i.e. within 500m from the Project Site) in HKSAR.  Schools, residential dwellings and a sewage treatment works are identified to the north or northwest of the river within Shenzhen region.

Since the Project area is rural and no major air emission sources are identified, the existing air quality in the vicinity of the river is affected by general background air quality in the Pearl River Delta.

There is no EPD Air Quality Monitoring Station (AQMS) operating in the Study Area.  The nearest AQMS operated by EPD is located at Tai Po.  The means of annual average concentrations of air pollutants recorded at Tai Po’s AQMS from 2005 to 2009 are adopted to characterise the background air quality for the impact assessment.  However, as CO concentration is not measured at the Tai Po’s AQMS, the CO concentrations measured at Tap Mun’s AQMS are used to establish the background CO concentration for the Study Area.  The background air quality for the Project is summarised in Table 4.2.

Table 4.2        Background Air Quality

Air Pollutant

Background Concentration (mg m-3) (a)

Total Suspended Particulates (TSP)

67

Respirable Suspended Particulates (RSP)

50

Nitrogen Dioxide (NO2)

51

Sulphur Dioxide (SO2)

16

Carbon Monoxide (CO)

745 (b)

Notes:

(a)     Arithmetic mean of annual average data on air pollutant concentrations measured at the EPD Tai Po AQMS for the period from 2005 to 2009. (http://www.epd-asg.gov.hk/english/report/aqr.php).

(b)     Since CO concentration is not measured at Tai Po’s AQMS, the CO concentrations measured at Tap Mun’s AQMS are used due to the similar environment to the Study Area.

4.4                                      Identification of Air Sensitive Receivers

The major landuse within the Study Area is village environs and no commercial or industrial establishments were identified.  Representative Air Sensitive Receivers (ASRs) were identified in line with the requirements set out in the EIA Study Brief (ESB-199/2004) and Annex 12 of the EIAO-TM.  They are summarised in Table 4.3 and illustrated in Figure 4.1.  The list includes existing and planned ASRs within the Study Area.  The Study Area is now covered by the Development Permission Area (DPA) Plans.  The planned ASRs were identified with reference to the relevant planning studies such as the Land Use Planning for the Closed Area.

Table 4.3        Representative Air Sensitive Receivers (ASRs)

ASR

Location

Type of Uses (a)

Approx. Distance from the nearest Project Site Boundary (m)

Approx. Max. Height of Building
(m above ground)

A1

Muk Wu Chuen Yiu

R

400

10

A2

Ta Ku Ling Ling Ying Public School

G/IC

387

3

A3

Chow Tin Tsuen

R

458

10

A4

Fung Wong Wu

R

390

10

A5

Ta Kwu Ling Village

R

11

10

A6

Ta Kwu Ling Police Station

G/IC

72

10

A7

Ta Kwu Ling Fire Station

G/IC

115

6

A8

ArchSD Property Services Branch

G/IC

100

3

A9

Kan Tau Wai

R

240

10

A10

Kaw Liu Village

R

11

10

A11

Tsung Yuen Ha

R

232

10

A12

Chuk Yuen Village Resite (b)

R

320

10

A13

Proposed Future Recreation Use (c)

Re

77

10

A14

Kan Tau Wai Village House

R

352

10

Notes:

(a)       R = Residential premises, G/IC = Government/Institution/Community, Re = Recreation

(b)       With reference to the EIA of the proposed Liangtang/Heung Yuen Wai Boundary Crossing Point (LT/HYW BCP), the relocation of Chuk Yuen Village will be completed by early 2013, before the commencement of the Shenzhen River Regulation Stage 4 works and the construction of the LT/HYW BCP Project.  Therefore instead of the existing Chuk Yuen Village, the future Chuk Yuen Village Resite will be included in the dust modelling and impact assessment.

(c)       With reference to the Land Use Planning for the Closed Area – Feasibility Study, recreational use was proposed in the area by the Planning Department.  While detailed plans for air sensitive uses are not readily available, this location is chosen for assessment of potential air quality impacts in the proposed recreation area.

4.5                                      Potential Sources of Impact

4.5.1                                Construction Phase

The construction phase of the Project will last for 44 months (ie August 2013 to March 2017, tentatively).  An advance work contract on the reprovisioning of boundary fence and patrol road on Hong Kong side, as part of this Project, will last for about 36 months between the period of February 2012 and January 2015, tentatively.  

Advanced Works – Reprovisioning of Boundary Fence and Patrol Road on Hong Kong Side

Reprovisioning of patrol road and boundary fence within the Project Site boundary has been described in Section 3.2.  The major construction activities may include excavation, footing construction, fence installation, road construction and demolition/relocation of existing boundary fence.  Given that the reprovisioning works will be carried out section by section and the road is narrow, the volume of excavated materials or filled materials required will be limited at any one time.  With the implementation of dust mitigation measures stipulated in Air Pollution Control (Construction Dust) Regulation, the dust impact will be alleviated and the advanced works will not cause any adverse air quality impact.

River Modification and Associated Works

River diversion will be carried out before the commencement of the construction of the regulation works.  The main construction works include dredging of river sediment, soil excavation, embankment construction, dry weather flow interception works, and landscaping works.  Detailed construction methodology has been described in Section 3.4.

The Project Site will be divided into four works areas along the river as shown in Figure 4.1. 

The construction works will be carried out from the downstream to upstream of each works area.  In accordance with the works programme, latest engineering design and the experience from Shenzhen River Stage 3 regulation works, the maximum size of the active construction areas at any one time will not be larger than 150m long along the river at each works area.

Construction dust is the major air quality concern during the construction phase.  Truck movements, excavation works, embankment construction, dry weather flow interception works, patrol road and boundary fence re-provisioning and wind erosion were identified to be the major dust generating activities.

Based on the latest engineering design, it is estimated that about 51,000 m3 of construction and demolition (C&D) materials and sediments will be excavated from the Project during the peak construction month.  About 8,500m3 of the excavated materials will be reused on-site and the rest (about 42,500m3) of excavated materials will be temporarily stored in the four stockpiling areas located on the Shenzhen side of the river bank (see Figures 3.14 to 3.17) for subsequent disposal off-site.  Dust emission from construction vehicle movements to and from the stockpiling areas and works areas will generally be limited within the work areas. 

During peak construction period, the disposal of surplus C&D materials and sediments will generate a maximum of 34 truck trips per hour to Yan Fang Road on the Shenzhen side ([1]).  Wheel washing facilities will be provided at all designated vehicular exit points and the dusty materials will be transported by vehicles with mechanical cover/tarpaulin.  With the implementation of the dust control measures recommended in Section 4.8.1, dust nuisance from construction vehicle movement outside the work areas is unlikely to be significant.

Dredging of river sediment will be required for the river modification works.  Depending on the quality of the river sediment, the dredging and handling of river sediment may cause odour impact during construction.  Hydrogen sulphide (H2S) is the key odour constituent of the dredged sediment.  With the implementation of good site practice recommended in Section 4.8.1, the odour nuisance is not anticipated.

4.5.2                                Operation Phase

As mentioned in Section 3.5, the frequency and scale of maintenance dredging required along the river channel and the flood retardation pond is anticipated to be very small compared with the dredging works during the capital works.  Besides, the dry weather flow interception works under this Project will convey the untreated sewage from the Shenzhen side, which currently are discharging into the Shenzhen River, into the Luo Fang sewage treatment work.  Therefore it is expected that the water and sediment quality will be improved after completion of the Project.  Thus adverse odour impacts on ASRs due to maintenance dredging are not expected.

Access to the reprovisioned Boundary Patrol Road (BPR) is controlled by the Frontier Closed Area (FCA) Permits issued under Section 37(2) of the Public Order Ordinance and only limited numbers of vehicle with valid permit can access to the Study Area.  Based on the approved “Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road – EIA Report”, it is anticipated that the traffic flow of the BPR will not exceed 50 vehicles per hour in 15 years after commissioning.  Adverse air quality impact due to traffic emission from the BPR is therefore, not envisaged.

4.5.3                                Concurrent Projects

Construction Phase

The works area of the planned LT/HYW BCP is located adjacent to the Works Area II and III of this Project and the EIA for LT/HYW BCP is ongoing.  Based on the latest best available information from the Design Engineer of LT/HYW BCP, the construction of the LT/HYW BCP and connecting roads will commence at the end of 2013 and be completed in end 2018.  It is anticipated that the LT/HYW BCP will be constructed concurrently with this Project.  With close liaison with the LT/HYW BCP project team, the latest best available dust emission sources information of the LT/HYW BCP project have been incorporated into the construction phase cumulative air quality impacts assessment of this EIA study. 

Based on the approved EIA report of the Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road (BPR) (Register No.: AEIAR-136/2009), the construction works will be carried out in phase and therefore the fugitive dust impact during construction will be minimal.  Of particular note, the construction of the section of fence and patrol road within the Project Area will be carried out under this Project and will be considered in this construction dust impact assessment.

Operation Phase

Within 500m study area, it is identified that the operation of the future LT/HYW BCP and reprovisioned BPR may cause cumulative impact with this Project.

Since the potential air quality impact from the operation of the BPR is also minimal as mentioned in Section 4.5.2 above, the cumulative impact on air quality is considered to be minimal.

The vehicular emissions from open roads and emissions from kiosks, loading and unloading (L&UL) areas and public transport interchange (PTI) arising from the operation of the future LT/HYW BCP may cause potential cumulative impacts with this Project.  Nitrogen dioxide (NO2) and respirable suspended particulates (RSP) are the key pollutants.  Based on the latest best available information from the project team of LT/HYW BCP, the predicted NO2 and RSP impacts at the identified ASRs are well within the AQOs.  As mentioned in Section 3.5 of this Project, the frequency and scale of maintenance dredging required along the river channel is low and the dredged sediments will be disposed of by marine vessels or trucks at Shenzhen side.  With respect to the small quantity of sediments to be dredged, a small number of truck trips will be generated from the handling and transportation of the dredged sediments.  It should be noted that the dredged sediments will be delivered to a pier in Shenzhen via the local route network in Shenzhen.  It is not anticipated that there will be adverse cumulative air quality impacts to the identified ASRs due to the minor NO2 and RSP emissions generated from such infrequent and small number of truck trips.

An on-site sewage treatment work (STW) is proposed to be built at the LT/HYW BCP to treat the sewage generated from the operation of BCP and the Chuk Yuen Village Resite and odour generated from the proposed STW at the BCP may also pose odour impact on nearly ASRs.  Based on the latest best available information from the project team of LT/HYW BCP, the STW is designed with odour containment and control measures to avoid or minimise odour emission from the operation of the STW.  With proper implementation control measures, no adverse odour impact is anticipated due to the operation of STW.  Again, as the frequency and scale of maintenance dredging required along the river channel is low, the quantity of dredged sediments will be much less than that to be dredged during the construction phase.  The dredged sediments will be disposed off-site immediately and no on-site stockpile of dredged sediment is required.  Cumulative odour impact is therefore considered to be minimal and would not cause adverse odour impacts at the nearby ASRs. 

4.6                                      Assessment Methodology

4.6.1                                Construction Dust

The key dust emission sources during construction phase of the Project include:

·           heavy construction (including excavation, embankment construction, dry weather flow interception works, construction of boundary fence and patrol road, on-site traffic etc.);

·           material handling at stockpiling area; and

·           wind erosion of open sites. 

The dust (in terms of Total Suspended Particulates (TSP)) emission rates associated with the principal dust sources during the construction phase of the Project have been estimated based on the typical emission factors reported in the Compilation of Air Pollution Emission Factors (AP-42) 5th Edition published by US Environmental Protection Agency (USEPA) and are presented in Annexes A1 and A2.  Unmitigated and mitigated scenarios were assessed.  Mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulations were considered in estimating the mitigated dust emission rates.  The unmitigated and mitigated dust emission factors are summarised in Table 4.4.

Table 4.4        Dust Emission Factors

Works Sites

Source Type

Dust Emission Factors

Remarks

Active work areas
(A1 to A7, B1 to B8, C1 to C5, D1to D6)

Heavy Construction

E = 2.69 Mg/hectare/month (unmitigated)

 

E = 0.269 Mg/hectare/month (mitigated)

·     AP-42, S13.2.3 1/95 Ed.

·     applied to all active works area

·     90% dust suppression (reference to Control of Open Fugitive Dust Sources, Section 3.3.3)

 

Wind Erosion

E = 0.85 Mg/hectare/year

·     AP-42, Table 11.9-4, 7/98 Ed.

Stockpiling Areas
(SP11, SP12, SP21, SP31, SP32, SP41 & SP42)

Earth Handling / Loading & Unloading

E= k x (0.0016) x ((U/2.2)1.3) / ((M/2)1.4)

 

E = 2.87E-04 kg/Mg (unmitigated)

 

E = 8.62E-05 kg/Mg (mitigated)

·     AP-42, S13.24, 11/06 Ed.

·     Particle size multiplier, k = 0.74

·     1.9 U, average wind speed, U = 1.9 ms-1 (Annual mean wind speed record at TKL weather station in 2008)

·     materials moisture content (%), M = 4.8%

·     70% dust suppression by watering at least 8 times a day

 

Wind Erosion

E = 0.85 Mg/hectare/year (unmitigated)

 

E = 0.255 Mg/hectare/year (mitigated)

·     AP-42, Table 11.9-4, 7/98 Ed.

·     70% dust suppression by watering at least 8 times a day

Hourly and Daily Average TSP

Based on the latest engineering design information, plant inventory presented in Annex B and the experience of Shenzhen River Stage 3 regulation works, the maximum active construction areas at any one time will not be larger than 150m long along the river at each Works Area.  For the assessment of maximum hourly and daily TSP concentrations at the identified ASRs, it is assumed that each Works Area will have a 150m long active working area at any one time during construction phase as a conservative approach.  In order to estimate the reasonable worst case for the ASRs, these active working areas will be located closest to the particular ASRs under two modelling scenarios:

·           Scenario 1: all active working areas are located to the southern part of Works Areas or closest to the ASRs A1 to A10 and A12 to A14 to assess the worst dust impacts; and 

·           Scenario 2: all active working areas are located to the northern part of Works Areas or closest to the ASR A11 to assess the worst dust impacts.

The locations of the active working areas under the two scenarios are shown in Figures A1 and A2 of Annex A1.  The implementation of dust control measures has also considered in the dust emission rate estimation.  The mitigated dust emissions are also summarised in Annex A1.

Annual Average TSP

Since the active working area will not be larger than 150m long along the river at any one time in each Work Area, the active working areas over the entire year will be about 10.5% of the works area for the whole project for predicting the annual TSP levels (please refer to Annex A2). 

The implementation of dust control measures presented in Section 4.8.1 has also considered in the dust emission rate estimation.  The mitigated dust emissions are summarised in Annex A2.

Modelling Approach

The cumulative unmitigated and mitigated 1-hour, 24-hour and annual average TSP concentrations at the representative ASRs due to the construction of the Project and the LT/HYW BCP have been predicted using the EPD approved air quality model Fugitive Dust Model (FDM).  During day-time (07:00 – 19:00 hrs), the dust emission rates from all potential construction activities have been considered while during remaining period (ie 19:00 – 07:00 hrs of the next day, hereafter referred to the night-time period), only dust emission from wind erosion of stockpiling areas has been considered as no construction works will be undertaken during the night-time period ([2]) .  As identified ASRs are elevated, the TSP concentrations at 1.5m, 5m and 10m above ground at the ASRs were modelled.

A set of meteorological data of the year of 2008 (with more than 90% valid data) were obtained from Hong Kong Observatory and used for the dust modelling:

·         Hourly wind direction and speed, air temperature and atmosphere Pasquill stability class obtained from Ta Kwu Ling Automatic Weather Station; and

·         Daily morning and maximum mixing heights based on the radiosonde ascent at King’s Park.

Particle size distribution is made reference to Section 13.2.4.3 of Compilation of Air Pollution Emission Factors (AP-42) 5th Edition.  The particle size distribution adopted in this assessment is presented in Table 4.5.

Table 4.5        Particle Size Distribution

Particle size (mm)

Distribution (%)

1.25

7

3.75

20

7.5

20

12.5

18

22.5

35

The highest unmitigated and mitigated maximum hourly TSP concentrations predicted at each ASR for day-time and night-time period were selected to represent the worst hourly TSP concentration at the ASR.  The daily averaged TSP concentrations predicted for day-time and night-time periods were summed up to obtain the 24-hour average TSP concentrations at the ASR.  Similar approach was adopted to obtain the annual average TSP concentrations.

The background TSP presented in Table 4.2 was added to the 1-hour, 24-hour and annual average results to obtain the overall TSP concentrations.

4.6.2                                Odour Emission from Dredged River Sediment

Sediment samples were taken at 3 locations along the river (see Figure 4.2).  The levels of acid volatile sulphide (AVS) in the river sediment of the Project Site were analysed to assess the potential odour impact during dredging and handling of the river sediment.  These sampling locations covered the upstream, middle and downstream sections of the river within the Study Area.

In general, sediment with a high AVS concentration has the potential to emit odorous hydrogen sulphide (H2S) gas.  The AVS levels of the river sediment samples were then compared with that measured from sediment considered to have minimum odour impact to the surrounding environment to evaluate the potential odour impact.  Reference to other similar projects was also made.

4.7                                      Evaluation of Impacts

4.7.1                                Construction Phase

Construction Dust

The cumulative unmitigated and mitigated 1-hour, 24-hour and annual average TSP concentrations were predicted at the identified ASRs and they are presented in Tables 4.6 and 4.7.  Detailed calculation of TSP modelled results was presented in Annex A3.

 

Table 4.6        Predicted Cumulative Unmitigated TSP Concentrations at ASRs

ASR

Predicted Cumulative Unmitigated TSP Concentrations (µg m-3) (a) – (d)

 

Maximum 1-hour TSP

24-hour Average TSP

Annual Average TSP

 

1.5m

5m

10m

1.5m

5m

10m

1.5m

5m

10m

A1

233

241

223

99

102

100

74

74

74

A2

432

450

407

94

96

93

70

70

70

A3

647 (e)

664

582

131

134

129

71

71

71

A4

712

721

611

166

167

154

73

73

73

A5

3063

1559

865

998

587

300

103

92

83

A6

1826

1316

709

354

292

181

89

86

81

A7

1369

1161

626

313

248

198

82

80

78

A8

863

805

568

290

276

219

85

81

78

A9

878

801

542

247

238

195

76

76

75

A10

1569

1346

773

466

396

245

97

92

85

A11

1091

965

587

292

274

213

77

77

76

A12

408

414

363

135

137

131

75

75

75

A13

861

834

656

175

174

159

96

95

89

A14

411

416

363

136

138

131

75

75

75

TSP Criteria

500

260

80

Notes:

(a)     Scenario 1 for A1 to A10 and A12 to A14; Scenario 2 for A11

(b)     Background TSP concentration of 67 µg m-3 has been included.

(c)     Detailed results are presented in Annex A3.

(d)     Mitigated emission rates of LT/HYW project are adopted.

(e)     Bold figures are exceeding the relevant criteria.


Table 4.7        Predicted Cumulative Mitigated TSP Concentrations at ASRs

ASR

Predicted Cumulative Mitigated TSP Concentrations (µg m-3)

 

Maximum 1-hour TSP

24-hour Average TSP

Annual Average TSP

 

1.5m

5m

10m

1.5m

5m

10m

1.5m

5m

10m

A1

108

112

108

74

75

74

68

68

68

A2

134

139

132

73

73

73

67

67

67

A3

154

160

150

77

78

77

68

68

68

A4

144

148

140

83

83

81

68

68

68

A5

394

265

186

174

128

95

72

71

70

A6

257

202

143

102

95

86

72

71

70

A7

307

185

147

151

98

87

72

70

69

A8

361

160

149

107

93

86

75

70

69

A9

176

159

143

94

92

85

69

69

69

A10

230

205

149

114

106

94

72

71

70

A11

332

300

229

131

123

103

69

69

69

A12

175

166

144

102

103

98

70

70

69

A13

197

200

180

91

91

88

73

73

71

A14

168

166

144

103

104

99

70

70

69

TSP Criteria

500

260

80

Notes:

(a)     Scenario 1 for A1 to A10 and A12 to A14; Scenario 2 for A11

(b)     Background TSP concentration of 67 µg m-3 has been included.

(c)     Detailed results are presented in Annex A3.

Without implementing any mitigation measures, exceedances of TSP criteria were predicted at A3 to A11 and A13.  After implementing mitigation measures recommended in Table 4.4 and Section 4.8.1, no exceedance of TSP criteria was predicted at all identified ASRs with the implementation of the recommended mitigation measures. 

The highest cumulative unmitigated and mitigated TSP concentrations were both predicted at 1.5m above ground.  Besides, contour plots showing cumulative unmitigated and mitigated 1-hour, 24-hour and annual average TSP concentrations at 1.5m above ground in the vicinity were plotted.  Contours showing cumulative unmitigated TSP concentrations under different time averaging at 1.5m above ground are shown in Figures 4.3 to 4.7 while contours showing cumulative mitigated TSP concentrations under different time averaging at 1.5m above ground are shown in Figures 4.8 to 4.12. 

The contour plots show that cumulative mitigated TSP concentrations within most of the Study Area complied with the respective TSP criteria but exceedance of TSP criteria is predicted at small areas immediately adjacent to the Project’s works area.  However, no ASRs are identified within the affected areas and therefore, no adverse dust impact is anticipated.

Odour from Dredged Sediment

The levels of AVS in the river sediments of the Project Site were analysed to identify the potential odour strength from the dredged sediment.  The AVS levels of the sediment samples were in the range of 2 to 30 mg kg-1.  The laboratory analysis report of AVS level in the sediment samples is attached in Annex A4. 

The AVS levels of remediated sediments, which are considered to have minimum odour impact to the surrounding environment, stated in an approved EIA report are in the range of 50 to 500 mg kg-1 ([3]).  These levels were used to compare with the AVS levels of the river sediments to be dredged under this Project to determine the potential odour impacts from dredging and handling of the sediment. 

The AVS concentrations in the sediment samples for this Project are significantly lower than the reference level.  In addition, the dredged sediment will be stored in enclosed tanks and will be delivered off-site for disposal every day.  It is therefore expected that the potential odour emissions from the dredging and handling of river sediments would be minimal.

4.7.2                                Operation Phase

Odour from Maintenance Dredging

As discussed in Section 4.5.2, the frequency and scale of maintenance dredging required along the river channel and the flood retardation pond is anticipated to be very small compared with the dredging works during the capital works.  Hence, by adopting similar mitigation measures as in the construction stage, adverse odour impacts at the ASRs due to maintenance dredging are not expected.

As mentioned above, the dredged sediments will be disposed of by trucks or marine vessels at Shenzhen side and the number of truck trips or marine vessels generated will be minimal.  With limited quantity of sediments dredged and the small number of truck trips at Shenzhen side or marine vessels generated in this Project, no adverse cumulative air quality impacts are anticipated at the identified ASRs.

4.8                                      Mitigation Measures

4.8.1                                Construction Phase

The following dust control measures stipulated in the Air Pollution Control (Construction Dust) Regulation will be implemented to reduce the fugitive dust emission as much as possible:

·         Water spaying on haul roads and dusty areas for every hour during the construction,

·         Covering the stockpile areas of at least 70% area with tarpaulin sheet or impervious sheet;

·         Covering of dusty materials/spoils on trucks by impervious sheets;

·         Controlling the dropping height of fill materials;

·         Covering or storing all debris and materials in a sheltered debris collection area;

·         Storing dredged sediment in a separate enclosed tank; and

·         Providing wheel washing facility at each exit of the works site.

Good site practices such as regular maintenance and checking of the diesel powered mechanical equipment will be adopted to avoid any black smoke emissions and to minimize gaseous emissions.

Dredged sediment placed on truck or marine vessel for disposal should be properly covered during transportation to minimise the potential odour.  In the event that dredging material are found to be odorous, the odorous dredged sediment should be placed as far away from the identified ASRs as practically possible and should be removed off-site as soon as practicable to avoid any potential odour nuisance arising.

4.8.2                                Operation Phase

The maintenance dredging may be undertaken by land-based or marine-based plants depending on the maintenance dredging strategy to be developed in future.  In order to minimize the potential odour emissions, if any, the dredged sediment placed on truck or marine vessel for disposal should be properly covered as far as practicable during transportation.  In the event that dredging material are found to be odorous, the odorous dredged sediment should be placed as far away from the identified ASRs as practically possible and should be removed off-site as soon as practicable to avoid any potential odour nuisance.

4.9                                      Residual Impacts

4.9.1                                Construction Phase

No residual impact is anticipated after the implementation of the recommended mitigation measures described in Section 4.8.1.

4.9.2                                Operation Phase

No residual impact is anticipated.

4.10                                  Environmental Monitoring and Audit (EM&A)

4.10.1                            Construction Phase

Regular environmental audit will be conducted to ensure the implementation of the recommended dust control measures for both the Advanced Works and River Modification and Associated Works.  Besides, dust levels, in terms of TSP will be monitored, at Ta Kwu Ling Village (AM1) and Tsung Yuen Ha (AM2) during River Modification Works in works area III or IV and works area I or II, respectively.  The location of proposed dust monitoring stations is shown in Figure 4.13.  Monitoring of 24-hour and 1-hour TSP levels will be conducted once every six days throughout the construction period.  Detailed EM&A requirements for dust monitoring are presented in the EM&A Manual. 

4.10.2                            Operation Phase

Since no adverse air quality and odour impacts are anticipated, no EM&A will be required.

4.11                                  Conclusions

4.11.1                            Construction Phase

Construction dust generating from the soil excavation, embankment construction, dry weather flow interception works, landscaping works, patrol road and boundary fence re-provisioning and odour from dredging and handling of river sediment are the key air quality concerns during construction phase. 

With the implementation of the recommended dust control measures and good construction site practices as recommended in Section 4.8.1, the construction of the Project will not cause adverse dust and air quality impacts.

The measured AVS concentrations in the sediment samples of the Project Site were well below of that for the remediated sediments, which are considered to have minimum odour impact to the surrounding environment.  The dredged sediment will be stored in enclosed tanks and will be delivered off-site for disposal at regular interval.  Therefore, potential odour impact due to dredging and handling of river sediment will be minimal.

It is recommended that regular environmental site audit should be conducted to ensure the implementation of recommended dust control measures and monitoring of 24-hour and 1-hour TSP levels should be carried out at the proposed dust monitoring stations at Ta Kwu Ling Village (AM1) and Tsung Yuen Ha (AM2) throughout the construction period to ensure no adverse dust impacts to the ASRs.

4.11.2                            Operation Phase

The frequency and scale of maintenance dredging required along the river channel and the flood retardation pond is anticipated to be very small compared with the dredging works during the capital works.  Besides, the dry weather flow interception works to be carried out under this Project will convey the untreated sewage from Shenzhen side, which are currently discharging to the Shenzhen River, to the sewage treatment work at Shenzhen.  It is therefore expected that the water and sediment quality of the Study Area will be improved after completion of the Project.  The potential odour emissions due to the dredging and handling of sediment associated with maintenance dredging will be minimal.  With the infrequent dredging activities required, limited quantity of sediments dredged and limited number of truck trips at Shenzhen side or marine vessels required, no adverse cumulative air quality impact is anticipated.

 



([1])  Based on typical truck loading capacity of 7m3, typical bulk factor of 1.4 (with reference to other approved EIA reports) (the excavated materials are mainly soft material), 10 working hours per day and 25 working days per month with reference to Shenzhen River Stage 3 experience, a maximum total of 34 trucks trips will be generated per hour during peak construction period (42,500*1.4/(7*25*10)).

([2])       12 hours daytime and 12 hours night-time are assumed to cover both 10 working hours for this Project and 12 working hours for LT/HYW BCP project as confirmed by LT/HYW BCP's project team as worst case assessment.

([3])       Dredging Works for Proposed Cruise Terminal at Kai Tak - Environmental Impact Assessment Report, Register No.: AEIAR-115/2007.